Modeling (2)
A top represents the end of work, null duration and succeeding all work without successor.
The graph associated with a project is without circuit and has only one top without predecessor (the top ) and only one top without successor (the top ).
To determine the minimal duration of a project realization amounts calculating a longer way between the tops and associated graph.